8.0 Installation
21
8.7 Making The Electrical Connections
To connect the mains input cable proceed as
follows:-
1. Slacken the facia securing screws and lift the
outercase panel so that it’s securing tabs are
clear of the facia. Remove the panel.
2. Remove the screws securing the facia panel
and hinge it down (Fig. 35).
3. Remove the control box cover securing
screws. Disengage the barbs on the control box
from the cover. Remove the cover (Fig. 33).
4. Slacken the cable clamp on the LH side of the
boiler chassis. Insert the cable through the clamp
and route it to the terminal block (Fig. 34).
5. Slacken the screws in the terminal block,
connect the input cable, and tighten the screws.
6. If an external control is to be connected it can
be done at this point. Run the input cable from
the external control through the second cable
clamp on the boiler chassis. Refer to the
instructions supplied with the control.
7. Remove the link between terminal 1 and 2 and
connect the wiring from the external control
(Figs. 36 & 37).
NOTE: If the room thermostat being used
incorporates an anticpator it MUST be wired as
shown in Fig. 37.
IMPORTANT: The external control MUST be
suitable for 230V switching.
8. Ensure that both mains input and, where
fitted, external control input cables have
sufficient slack to allow the control box to drop
down. Tighten the cable clamp(s) on the boiler
chassis.
9. If the optional integral timer is to be used it
should be fitted at this point. Refer to the
instructions supplied with the timer. NOTE: An
external frost thermostat cannot be used with the
integral timer.
8.8 Preliminary Electrical Checks
1. Prior to commissioning the boiler preliminary
electrical system checks should be carried out.
2. These should be performed using a suitable
meter, and include checks for Ground Continuity,
Resistance to Ground, Short Circuit and Polarity.
Comments to this Manuals