7 Commissioning
7.6 Final Instructions
1. Carefully read and complete all sections of the Benchmark
Commissioning Checklist at the rear of this publication that are
relevant to the boiler and installation. These details will be
required in the event of any warranty work.
2. The publication must be handed to the user for safe keeping
and each subsequent regular service visit recorded.
3. Hand over the User’s Operating, Installation and Servicing
Instructions, giving advice on the necessity of regular servicing.
4. For IE, it is necessary to complete a “Declaration of
Conformity” to indicate compliance with I.S. 813. An example of
this is given in I.S. 813 “Domestic Gas Installations”. This is in
addition to the Benchmark Commissioning Checklist.
5. Instruct the user in the operation of the boiler controls. Hand
over the User’s Operating, Installation and Servicing
Instructions, giving advice on the necessity of regular servicing.
6. Demonstrate to the user the action required if a gas leak
occurs or is suspected. Show them how to turn off the gas
supply at the meter control, and advise them not to operate
electric light or power switched, and to ventilate the property.
7. Show the user the location of the system control isolation
switch, and demonstrate its operation.
8. Advise the user that they may observe a plume of vapour
from the flue terminal, and that it is part of the normal operation
of the boiler.
9. Complete the label supplied with the inhibitor and stick to the
inside of the boiler case. Detail of system treatment must be
recorded in the Benchmark Commissioning Checklist.