Baxi Bermuda Inset 2 Boiler 50/4 EFireside Gas Central Heating UnitInstallation and Servicing InstructionsPlease leave these instructions with the use
4.0 Site Requirements10 14.5 Flue1. The flue installation must conform to BS 5440 Pt 1. The flue must have a minimumvertical height of 3m (10ft) and h
4.0 Site Requirements1 114.6 Ventilation1. Ventilation air supply to BS 5440 Pt 2 isrequired. The permanent ventilation area sizerequirements are as s
5.0 Electrical12Main Gas ValvePilot Gas ValveThermostat SensorControlPotentiometer& SwitchSpark ElectrodeNNExternalControlsS/LL230VLbrborppor/bkr/
6.0 Installation136.1 Initial Preparation1. Remove the outer carton from the boiler pack.Discard the packing pieces. Remove the boilerhood and fitting
6.0 Installation146.3 Connecting the Sensing Pipe1. Remove the protection cap from the sensingpipe adaptor on the burner mounting plate.Slacken the sc
6.0 Installation156.7 Water Connections1. The boiler has one return and two flowtappings, Rc1 (1in BSP). The flows are the twoupper tappings. The retu
6.0 Installation166.9 Pumped Heating & Gravity Hot Water (Fig. 17)1. A 1in x 22mm threaded adaptor, twocompression nuts and olives and a brass inj
6.0 Installation176.11 Electrical Connection1. The appliance requires an electrical supplyfrom the heating controls system.2. A permanent live supply
7.0 Commissioning the Appliance187.1 Commissioning the Appliance1. Reference should be made to BS 5449 section 5when commissioning the boiler and syst
8.0 Annual Servicing198.1 Annual Servicing1. To perform annual servicing of the back boilerit is necessary to remove the firefront. 2. After servicing
2Baxi UK Limited is one of the leading manufacturersof domestic heating products in the UK. Our first priority is to give a high quality service to o
8.0 Annual Servicing208.4 Cleaning the Lint Arrestor1. Remove the lint arrestor from its retaining clipson the burner mounting plate and clean away an
8.0 Annual Servicing218.7 Cleaning the Heat Exchanger1. Remove the top and the centre baffles fromthe heat exchanger, noting their orientation(Fig. 43
9.0 Changing Components229.1 Changing Components1. To change any components on the back boilerit is necessary to remove the fire front.2. After changi
9.0 Changing Components239.6 Printed Circuit Board 1. Remove the controls heat shield from itsretaining clips. 2. Undo the two screws retaining the va
9.0 Changing Components249.8 Gas Valve1. Remove controls heat shield (Fig. 58).2. Remove the screws holding the valve coverassembly to the controls mo
9.0 Changing Components259.10 Pilot/A.S.D. AssemblyWARNING: The Pilot/A.S.D. Assembly shouldnot be adjusted in anyway. The A.S.D. mustnot be altered s
10.0Fault Finding26Before starting FAULT FINDING carry outpreliminary electrical system checks i.e. EarthContinuity, Polarity, Short Circuit and Resis
10.0Fault Finding27WARNING: Where practicable fault findingshould be performed with the main electricitysupply ISOLATED.Ispilot/ASDassembly,sensingtub
2810.0Fault FindingCheck solenoidleads for continuityReplace P.C.B.Does“Boiler On”neon light ?Isresistanceacross sensor correct ?(1M OHM @ 25oC)Arepot
2911.0 Short parts listShort Parts ListKey G.C. Description ManufacturersNo. No. Part No.39 E02-416 Burner 23865260 378 882 Injector B19 23401451 E00-
31.0 Introduction 42.0 Technical Data 53.0 System Details 6Water Circulating SystemsTreatment of Water Circulating SystemsPipeworkSystem ControlsFully
3012.0Notes
31Baxi UK Limited manufacture a comprehensiverange of products for the domestic heating marketGas Central Heating Boilers(Wall, Floor and Fireside mod
Baxi UK LimitedBrownedge RoadBamber Bridge PrestonLancashirePR5 6SNwww.baxi.comThe Baxi HelplinesFor General Enquiries+44 (0)8706 060 780For After Sal
1.0 Introduction4 1STANDARDB.S. 6891B.S. 5546B.S. 5449B.S. 6798B.S. 5440: Pt 1B.S. 5440: Pt 2B.S. 5871: Pt 1B.S. 6500SCOPEGas Installation.Installatio
2.0 Technical Data1 5Bermuda Inset 2 Boiler 50/4 EThe Boiler is for use with Natural Gas only.Heat Input Max Mid MinkW 18.79 17 15.2Btu/h 64,100 58,07
3.0 System Details6 13.1 Water Circulating Systems1. The appliance is suitable for open ventedsystems which are either fully pumped or pumpedcentral h
3.3 Pipework1. The sizes of the flow and return pipes from theboiler should be determined by normal methodsaccording to the requirements of the system
3.0 System Details8 13.6 Storage Systems1. For information regarding the use of aBermuda Inset 2 boiler with a storage system,contact the appropriate
4.0 Site Requirements94.1 Builders Opening (Fig. 5)1. The boiler unit is designed to fit within astandard builders opening, the minimumdimensions of w